From Pipeline to Capacity: Building a Connected Demand Forecast
Translate likely opportunities into dated skill requirements without treating every possible deal as a confirmed assignment.
Read article →CLOUSYS / SOFTWARE EVALUATION GUIDE
Compare dated demand with skills, allocations and usable availability. Build a capacity plan that explains the commitments your services business can make.
Compare dated demand with skills, allocations and usable availability. Build a capacity plan that explains the commitments your services business can make.
A headcount target is not a capacity plan. Capture the role, skills, location, start date, duration and allocation required by the engagement. Keep tentative opportunities separate from confirmed work so that the plan reflects uncertainty rather than hiding it.
Contracted hours are only the starting point. Planned leave, existing assignments, internal commitments and working calendars change the time a person can offer. Partial availability matters as much as an upcoming release.
Bring the demand horizon alongside current bookings and expected releases. Review near-term commitments in more detail than speculative work further out. Agree how often owners will refresh dates and probability.
A capacity gap can lead to recruitment, redeployment, development, vendor participation or a revised delivery commitment. Compare the timing and operating constraints of each response.
Suppose a specialist has 40 contracted hours, eight hours of leave and four hours of internal commitments. Assignable capacity is 28 hours. A 24-hour booking leaves four hours available.
Extend, reduce or release bookings when project circumstances change. Tentative reservations should not silently become permanent commitments. Record who approved the change and which delivery plan it affects.
Capacity describes the time available to plan. Utilization describes how time was used or is expected to be used. State the denominator before comparing people, teams or periods.
Bring a real demand request, current allocations, leave and a forthcoming release. Ask the team to follow the decision from requirement to confirmed deployment.
Explore the records, decisions and handoffs your teams want to improve.